Construction Delay Claims: Protecting Your Right to Time and Money
Almost every project runs late somewhere. The answer to more time, more money, both or neither depends less on who caused the delay than on what the contract says and what the paperwork proves.

Three kinds of delay
| Type | Example | Time | Money |
|---|---|---|---|
| Excusable and compensable | Owner changes the design, late owner furnished equipment | Yes | Yes |
| Excusable, not compensable | Unusually severe weather, force majeure events | Yes | Mostly no |
| Non excusable | Contractor's own crews or suppliers fall behind | No | No; may owe damages |
When two causes overlap, one the owner's and one the contractor's, it is a concurrent delay. Many contracts and courts then allow time but no money.
Notice: the clause that loses most claims
Most contracts require written notice within a short window, often 7 to 21 days after the delaying event. Miss it and a valid claim can be waived. Put the notice in writing, cite the contract clause, describe the event and say that time and cost impacts will follow. You can price it later; you can't notify late.
Proving the delay
A claim needs to show the event pushed the critical path, the chain of activities that sets the finish date. Common methods include a time impact analysis, which inserts the delay into the current schedule, and an as planned versus as built comparison after the fact. Either needs a schedule that was updated honestly during the job.
The records that win
- Daily reports with crew counts, weather and what was blocked.
- Dated photos and video.
- RFIs and their response times, and late submittal approvals.
- Meeting minutes and emails confirming instructions.
- Cost records split by cause: idle equipment, extended site overhead, escalated materials.
Clauses to read before you sign
- No damages for delay. Limits the contractor to time only, even for owner caused delays. Some states restrict these clauses.
- Liquidated damages. A daily rate the contractor pays for late finish.
- Force majeure. Defines which outside events excuse delay; check if it covers supply chain failures and epidemics.
- Escalation. If material price rises during a delay can be recovered; see supply chain planning.
Underbid jobs and claims
A bid priced to win rather than to build leaves no room for the normal surprises of a project. The contractor then looks to claims to recover the gap, the owner resists, and both sides lose time and legal fees. Nobody wins when a project is underbid. Owners do better comparing bids on scope and schedule, not price alone.
Frequently asked questions
What is a compensable delay in construction?
A delay caused by the owner or its agents, such as design changes or late approvals, that entitles the contractor to both extra time and extra cost under the contract.
How long do you have to submit a delay claim?
It depends on the contract. Many require written notice within 7 to 21 days of the event, with the detailed claim following later.
What is a no damages for delay clause?
A clause that limits the contractor to an extension of time, with no extra money, even when the owner causes the delay. Some states limit their use.