Shop Drawings and Submittals 101
Submittals are how a contractor shows the design team exactly what it plans to install before buying it. Shop drawings are one kind of submittal, and on most projects they are the one that holds up the schedule.

Submittals and shop drawings: the difference
A submittal is any document the contractor sends for review to show that materials and systems meet the contract. A shop drawing is a submittal drawn by the fabricator or subcontractor showing how a component will be made and installed: steel connections, ductwork routing, curtain wall details, millwork.
| Type | What it shows | Example |
|---|---|---|
| Shop drawings | Fabrication and installation details | Structural steel connections |
| Product data | Manufacturer sheets and specifications | Rooftop HVAC unit data sheet |
| Samples | Physical finish or color | Brick, carpet, paint draw downs |
| Mockups | A built sample on site | Window and wall assembly |
| Certificates and tests | Compliance proof | Fire ratings, mill certificates |
Who does what
- The subcontractor or supplier prepares the submittal.
- The general contractor reviews it against the contract and coordination with other trades, then stamps and forwards it.
- The architect or engineer reviews it for conformance with the design intent and returns it with a stamp.
The process and timing are normally set in Division 01 of the specifications, under 01 33 00 Submittal Procedures in the CSI MasterFormat system.
The review stamps
- Approved / no exceptions taken. Proceed.
- Approved as noted. Proceed, incorporating the comments.
- Revise and resubmit. Fix and send again before ordering.
- Rejected. Does not meet the contract.
Approval does not change the contract. If a shop drawing shows something different from the specification, call it out clearly, or the contractor may still be held to the original requirement.
Keeping submittals off the critical path
- Build a submittal log at the start, listing every required item, its spec number, responsible trade, required date and lead time.
- Prioritise long lead items; their fabrication clock often starts only at approval (see supply chain planning).
- Agree review times in the contract, commonly 10 to 14 working days, and track them.
- Send complete packages; partial submittals bounce back.
Late reviews are a common basis for delay claims, so log every date.
Frequently asked questions
What is the difference between shop drawings and submittals?
Submittals are all documents sent for design review, including product data, samples and certificates. Shop drawings are one type of submittal showing how a component will be fabricated and installed.
Who approves shop drawings?
The general contractor reviews and stamps them first, then the architect or engineer of record reviews them for conformance with the design.
How long does submittal review take?
Contracts commonly allow 10 to 14 working days per review, though complex packages can take longer.